Environmental Science & Engineering - www.esemag.com - January 2004
Comments? send them to the editor.

Mechanically stabilized embankment uses polyester geogrid reinforcement

Mark Simpson, P.Eng., Layfield Group Ltd.

Placement of secondary geogrid wrap.

Faced with significant environmental protection, cost, and operational constraints, the St. Lawrence and Hudson Railway (now Canadian Pacific Railway) chose to reinforce a deteriorating railway trestle bridge with a geogrid reinforced mechanically stabilized embankment.

In June 2000, the St. Lawrence and Hudson Railway commissioned the reconstruction of a 15m high x 60m long railway trestle bridge across a river valley in St. Thomas, Ontario. The overall design was developed by McCormick Rankin Consultants, with Thurber Engineering Ltd. carrying out geotechnical design, and construction was by J-AAR Contracting of London, Ontario. Layfield Geosynthetics Ltd. supplied the geosynthetic material and on-site installation supervision.

The trestle was replaced with a geosynthetic reinforced granular embankment constructed from the valley floor up to the base of the railway tracks at a 1:1 slope. A granular embankment was chosen over other structural techniques based on constraints such as reduction of environmental impact, land ownership cost, railway operations, and timing. Several unique construction techniques were utilized to ensure a fast and efficient project completion within a tight timeline.

Design constraints
The design engineer faced several design constraints including:

1. Operational - A key design consideration was to minimize the down time of the railway line. Re-constructing a new trestle bridge would have forced the closure of the railway line for an extended period of time. The mechanically stabilized embankment (MSE) design allowed the railway to remain open during most of the construction except for the short period of time when the tracks were removed to facilitate construction of the top portion of the embankment.

2. Environmental - Minimizing the impact on the environment is a challenge typically faced when crossing a river valley. Steepening the embankment slopes achieved three important objectives: 3. Hydraulic - Steepening the slope of the embankment also achieved two important hydraulic objectives: 4. Land ownership - Typically, if possible, it is best to keep construction works within the bounds of the railroad right-of-way. Going outside this boundary involves the purchase of more land at a high cost. Utilizing a steepened embankment design allowed the minimization of land area purchased.

Geosynthetic technology employed
There has been a dramatic expansion of reinforced soil structures in the United States and Canada over the last decade. The projection in the US is for over 70,000 square metres of new wall face per year. Geogrid reinforcement in slopes is typically used to achieve two objectives: increase slope stability, and to improve compaction at the edges of the slope to reduce sloughing.

As in this case, a typical MSE design employs two types of geogrid reinforcement, primary and secondary. The primary geogrid acts like reinforcing steel in concrete, adding strength in tension to the soil mass. Utilizing a high strength polyester yarn geogrid allowed the construction of a 45 degree embankment, utilizing OPSS 1010 Granular B Type 1 Soil with an angle of internal friction of 32 degrees.

Table 1. Geogrid lift spacing
1. Primary geogrid reinforcement - The primary geogrid reinforcement utilized in this design has a minimum long-term design strength (LTDS) of 60kN/m based on GRI-GG4(b) in Sand and Gravel. The geogrid is constructed of a high strength, low creep polyester yarn coated with a polymer for protection against UV degradation and mechanical damage. From the bottom to the top of the embankment, the spacing and strength of the geogrid is detailed in Table 1.

The lower strength geogrid and wider spacing could be utilized at the top of the embankment due to the reduced design loads that, in turn, provided a cost savings.

The primary geogrid was laid out in continuous lengths perpendicular to the slope face, through the trestle, to reinforce the granular soils in the embankment. A total of 11,200 square metres of primary geogrid was used in this project.

2. Secondary geogrid - The secondary geogrid reinforcement utilized in this design has a minimum LTDS of 6kN/m based on GRI-GG4(b) in Sand and Gravel. The secondary geogrid was constructed of polypropylene yarns with carbon black additive for protection against UV degradation. The yarns are also coated with a polymer for protection against mechanical damage and increased friction with the soil. The geogrid was utilized as a compaction aid at the extreme edges of each granular soil lift as well as to encapsulate the topsoil, seed, and erosion control blanket wrapped behind the geogrid. The secondary geogrid wrapped configuration was also used as an aid to minimize surface erosion and sloughing, which is often found in steepened slopes. A total of 13,500 square metres was used in this project.

Construction techniques
The primary geogrid was placed over each lift of granular. Of greatest importance was that the entire lift surface was covered with the geogrid with the strength direction oriented perpendicular to the slope face. To achieve this, and to reduce waste, incremental lengths of geogrid were manufactured, specific to the surface area of each lift. This also eliminated the need for splicing in the strength direction of the grid. The challenge of placing the geogrid around the vertical columns that remained in the trestle was overcome by simply slitting the geogrid in the direction perpendicular to the slope face (non-strength direction). This technique allowed for the maximum number of reinforcing bars around each column. The geogrid was then staked in place and the granular materials were pushed from the centre of the embankment toward the edges to ensure that the geogrid was tensioned in the process.

The secondary geogrid and erosion control blankets that comprised the wrap face were laid out in continuous lengths parallel to the slope face. The lower leg of the secondary grid was embedded a minimum 1.1m. The erosion control blanket was then placed in intimate contact with the secondary geogrid, then wrapped over the leading edge of embankment fill, topsoil, and seed. Finally, the upper leg of the geogrid was placed a minimum of 2m over the exposed surface of the top lift of granular material. Temporary forms and a skilled excavator operator maintained the alignment of the 1:1 slope as they progressed upward.

Post-construction follow-up
A site visit was performed in May of 2002, almost two years post-construction. The exposed slope faces were completely covered by dense native vegetation. At the inspection, the dense vegetation was pulled back to expose the secondary geogrid which was visually unaffected by the sun’s UV rays. The general contractor was pleased with the project, noting that it was completed on time and within budget. The contractor also noted that it was a unique and technically challenging construction project, which made it interesting to participate in.

Typical costs
Mechanically stabilized embankments consist of three primary components: the reinforcement, backfill, and face treatment. Typically, these costs, as a percentage of the total cost, break out as follows: In this case, constructing a reinforced steepened slope proved to be more cost-effective than an unreinforced, 2:1 slope alternative. In a simplified analysis, the reinforced embankment proved to be 15% less expensive to construct than a 2:1 unreinforced slope. This is a very conservative analysis since it does not account for the additional material required to construct the mandatory benched slope, the cost of a lengthened culvert, or the cost of additional land. Further, steep, unprotected slopes tend to require additional ongoing maintenance, particularly on the slope face due to sloughing and surface erosion. In this case the wrap wall construction protected against these maintenance problems.

The project was successfully completed on time and within budget. Utilizing geosynthetic technology, the designer was able to overcome many of the constraints involved in building a steep slope in a narrow parcel of land. Mechanically stabilized embankments have become a much more common design practice with an evolving body of knowledge on the subject.


For more information, contact e-mail: msimpson@layfieldgroup.com. The author would like to thank Paulo Branco, Thurber Engineering, Barry Palynchuk, Canadian Pacific Railway, Kirk Smith, J-AAR Excavating and Pierre Boislard, Layfield Group Ltd. for their support with this article.

See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.