Environmental Science & Engineering - www.esemag.com - January 2004
Comments? send them to the editor.

Mountain stream bridged on Olympic route in British Columbia

By Philip Carroll, P.Eng.,Armtec Ltd.


Highway No. 99 in British Colombia represents the critical transportation route between the City of Vancouver and the Resort Municipality of Whistler, the sites of the 2010 Winter Olympics. After years of study, public input and preliminary design by UMA Engineering Limited, the existing route was divided into various sections and awarded to consulting teams for detailed design assignments under the supervision of SNC Lavalin Inc.

Detailed design for the 7.2 km road section between Culliton Bridge and Cheakumus Canyon (approximately a half hour drive north of Squamish and south of Whistler), was prepared by Earth Tech Canada Limited, widening the road to three lanes and straightening its vertical and horizontal alignment to improve driver safety. Conroy Creek, a mountain stream, home to a resident population of Rainbow Trout, crosses Highway No. 99 in this section of highway via an existing Multi-Plate Pipe Arch, measuring approximately 2.4m wide x 2.1m high.

As part of the design process, Armtec provided pre-design technical support to Earth Tech by offering a Bridge-Plate cross-section shape suitable for the span, rise, cover and hydraulic end requirements for the crossing. To provide improved fish passage, the structure was designed to be on a flat gradient, having an open bottom arch design with a span of 10.247m and rise of 4.843m.

As part of the tender and quotation process, Armtec prepared and distributed a set of preliminary installation and assembly drawings for a 30.08m long Bridge-Plate Structure along with a preliminary design for cast-in-place concrete footings and gravity end walls. Following award of the $18.2 million dollar construction contract to Bel Contracting Limited, Armtec provided input on how the structure could be lengthened to reduce and/or eliminate the need for the end walls.

After detailed analysis by Bel and Armtec, the structure was lengthened to 33.68m and the upstream end wall was eliminated in favour of a rip-rap/non-woven geotextile (Armtec 350) slope and cast-in-place end collar. The downstream end was redesigned with a cast-in-place end collar in conjunction with Lock-Block wingwalls, reinforced with Armtec Mirafi 8XT Polyester Geogrid.

Armtec retained McElhanney Consulting Services to offer detailed design and field certification services for the cast-in-place concrete footings, downstream end wall and upstream slope treatments. McElhanney also conducted an overall geometry check of how the roadway fill slopes tied into the end walls.

Following installation of the 2m wide x 0.5m high footings by Newport Structures Limited, the 28 ring Bridge- Plate was assembled in approximately four days, with one and a half days extra for tightening.

With the support of an Armtec engineer to provide onsite quality control, Bel crews started installation of the critical backfill gravel compacting in 200mm high lifts on either side of the structure. Within four and a half days, Bel finished the majority of the backfill placement to approximately 1m above the crown of the structure. The Bridge- Plate Structure was assembled, tightened and backfilled in under 10 working days, making it possible to finish the project by the fish window deadline.

During the backfill process, Armtec provided continuous monitoring of the structure by installing six monitoring stations and logging chord measurements using a handheld electronic distance measurement (EDM) tool. Gravel quality and compaction tests were also monitored on an ongoing basis.

To armour the footings inside the structure without having to place large boulders against the Bridge-Plate and risking damage, Bel installed 25kg rip-rap directly above the footings and pumped concrete into the voids. To mimic a natural stream bed, the design also called for the placement of a 300mm thick layer of fish gravel above the riprap layer.

Following the removal of the stream diversion and restoration of the creek flow through the structure, Conroy Creek assumed the look of a pool area within the confines of the structure, a great resting place for the resident population of Rainbow Trout.

After a few weeks, the drainage area was subjected to a flood event of historical proportions and the Conroy Creek structure ran at/near its hydraulic capacity. With the concrete collars and end treatment design in place, the structure was able to accommodate the flood flows.


Philip Carroll is Armtec’s BC Region Engineer. Contact e-mail: pcarroll@armtec.com.

See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.