Environmental Science & Engineering - www.esemag.com - January 2004
Comments? send them to the editor.

TransCanada Highway served by concrete box culverts

By Ryan Finley, P. Eng. and
Khaled Nasery, E.I.T.

Preparing seal for placement of box unit.

The TransCanada Highway is the world’s longest national highway, stretching 7,821 km. It is vital to Canada’s economy that the highway be maintained without disruption and premature structural failures.

Use of precast concrete box units under the TransCanada Highway was based on past performance and the expected service life of precast reinforced concrete box culverts. At two crossings of the highway, one kilometre apart, cast-in-place double cell concrete box culverts were installed in 1955 to carry the flow of Hartell Creek. The culverts, located east of Calgary, Alberta, near the Town of Strathmore, were extended across new eastbound lanes with arched structural plate corrugated steel pipe (SPCSP) when this section of the highway was twinned in 1974.

Replacement culverts had to meet a 75-year design life as specified in the Canadian Highway Bridge Design Code (CHBDC). An advantage of precast box culverts was a better fit with the existing cast-in-place culvert.

Khaled Nasery, E.I.T. of Mish Engineering designed the culvert replacements under the supervision of Ash Morjaria, P.Eng. Mish Engineering presented Alberta Transportation with three different size pre-cast concrete box alternatives: The single 3 m span x 2.4 m rise boxes were chosen, based on cost and optimum sizing to handle the design flow, and awarded to Mesken Contracting Ltd. after being tendered in December, 2002. Lafarge Canada, Inc. supplied the box units from their Calgary pipe operation after designing the units in accordance with CHBDC for CL-800 truck loading and cover ranging from 0.2 m to 2.65 m above the top of the culvert. The 44 box units, each 2 m long, were produced in February, with AMEC Earth and Environmental inspecting the production. The west culvert required 19 units and the east culvert 25.
Construction took place in two stages. First, eastbound traffic was reduced to one lane and moved onto the south shoulder. The failed SPCSP was removed and 10 sections were installed at the west culvert and 11 at the east culvert. The first box units were cast with exposed reinforcing to facilitate an easy field connection to the existing culverts. After the first stage installation was backfilled, the contractor moved the traffic to the north shoulder over the newly installed boxes and installed the remaining box units at each site. The roadway was surfaced and the eastbound lanes opened to two-lane traffic. The westbound lanes were unaffected by the construction; however, eastbound traffic was reduced to one lane for 16 days at the west end, and 18 days at the east end. The contractor worked at both sites simultaneously on a 24-hour basis in extreme cold conditions. Construction was complete in 22 days at both sites. A steel strut was placed at the upstream end of the new culvert sections to block large debris, not for structural support.

Installation of the precast concrete box culverts provided minimal disruption to traffic and an economical, long-lasting product that will stand up to the existing environmental and load conditions.


Ryan Finley is with Lafarge Canada, Inc., and Khaled Nasery is with Mish Engineering, Ltd. Contact ryan.finley@lafarge-na.com for more information.

See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.