Environmental Science & Engineering - www.esemag.com - January 2005
Comments? send them to the editor.

Lined reinforced concrete pipe
is a first for London, Ontario

By Neil Wyatt

Welding pipe joint at pre-lined MH connection.
To improve the environment of a London, Ontario, neighbourhood and solve major structural problems caused by sulphuric acid (H2SO4), a 675 mm diameter concrete sanitary sewer commissioned in the late 1960s was replaced with a specially designed 590 metre precast concrete system. Residents along Gordon Avenue brought the problem to the attention of City officials when they began reporting a strong odour of rotten eggs, associated with the presence of hydrogen sulphide gas (H2S). Evidence of a major problem with the sanitary sewer line mounted when homeowners complained about deteriorating piping in their houses that needed repair by licensed plumbers. Inspections of a major maintenance hole at the intersection of Commissioners Road and Gordon Avenue followed, along with video inspections of sections of the sanitary trunk sewer. It was clearly evident that the sanitary sewer had been aggressively attacked by H2SO4 and sections were in need of replacement.

The Gordon Avenue trunk sewer begins near Hooks Restaurant (Wharncliffe Road and Southdale Road) where it receives the flow from the Dingman Pumping Station. From there, the sewer weaves through a combination of streets and easements as it directs flows to the Greenway treatment plant by the Thames River. Overall, the length is approximately 4,500 metres, with pipe sizes from 675 mm to 1200 mm diameter. The 590-metre section of this project is just the first problem area that will be addressed by the City over the coming years.

The line of reinforced concrete sanitary sewer, installed around 1967, had been designed to receive effluent from the Dingman pumping station. Composition of the effluent was undetermined, and even today with a sewer use by-law in place, there are concerns that aggressive chemicals are entering the effluent from unknown sources. Although the concrete pipe had significant damage to the crown of the pipe, it was still structurally sound, but too costly, and almost impossible technically, to repair. The new sewer was designed with an increased diameter to reduce the velocity of the effluent and the turbulence that contributes to the production of H2SO4. Designers decided to replace an aging waterline and also a storm sewer while Gordon Avenue was under construction.

The maintenance hole at the intersection of Commissioners Road and Gordon Avenue contributed significantly to the premature deterioration of the sanitary sewer in two ways. First, the 90-degree bend in flow for the sewage created a very turbulent situation, which combined with other environmental conditions in the sewer to generate H2SO4. Flows into the structure were expected to be in the range of 2.5 to 3.5 million gallons per day. In fact, the flows were found to be in excess of 6 million gallons per day.

Secondly, the inspections of the system discovered a 2-inch x 4-inch timber, about 8 feet long, that appeared more like a railway tie because of the build-up of debris on it. The timber had lodged in the flow-through maintenance hole which was also creating turbulence and helping generate H2SO4. These two factors contributed to the corrosion in the maintenance hole and left an unstable situation which the City discovered as they entered the maintenance hole. When lowered into the maintenance hole, the inspector reached for the ladder rungs and discovered the reinforcing steel was more than accessible to his hand. Considering the level of corrosion, the City took action to cover the flow with some piping, and then fill in the maintenance hole with concrete. One can speculate that conditions in this maintenance hole had contributed significantly to the premature deterioration of the sanitary sewers in the area.

The solution that engineers devised to protect the new reinforced concrete sanitary sewer was to enhance its structural performance with a liner. This solution will extend the service life of the system well into the 22nd century, barring any further unforeseen hydraulic or effluent composition changes to the sewage from the catchment area or internal environment of the system. Production of the lined pipe and installation by the contractor were carefully planned, engineered, and documented according to the best available knowledge. The installation of this product is a first for the City of London, and one of only a few in all of Canada.

Lined reinforced concrete pipe is available in Ontario, and may be used where special circumstances warrant. Small diameter reinforced concrete pipe does not need to be lined to collect and carry common sanitary sewage.

Hanson worked with the installation crew of Elgin Construction to devise a technique for joining the liner in the field with 10-inch flaps covering the joints, after the sealed joints of the concrete pipe had been properly homed. Hanson produced 260 units of lined 900 mm and 1200 mm diameter pipe in its Cambridge plant. Liners were incorporated into the pipe as it was being produced, and seams welded in-plant before shipment to the site. The seams were located at the crown of each pipe, and Swift Lift anchors located on the barrel so that when pipe was lowered into the trench, the seam location would be consistent along the crown. Installation crews were then able to enter the pipe and weld liner flaps to the liner of the homed pipe to provide a completely sealed interior space with little impact on the hydraulics of the system.

Delcan, the consulting engineering firm for the project, had to design the project so that the flows would not be interrupted until it was time to decommission the old line and connect the new. Engineering called for the construction of a larger diameter parallel line, complete with lined maintenance holes, to a location where the new line would cross over the trench to connect with the existing sewer, approximately 590 metres upstream from the maintenance hole at the intersection of Gordon Avenue and Commissioners Road. As the new system was being constructed, a 300 mm reinforced concrete storm sewer was also installed.

Construction was required along the existing paved portion of Commissioners Road at a depth of approximately 7 metres, while maintaining the flow of through-traffic. A trench box was required, along with a series of steel I-beams placed across the top of the open trench to support the exposed watermain and utility conduits during the installation of the sanitary sewer.

On Gordon Avenue, the engineers designed and placed the new sanitary sewer along the line of the old storm sewer, and placed the new storm sewer along the line of the old sanitary sewer, ending with a complex crossover of the sanitary and storm sewers at the upstream end of the project. The sanitary sewer maintenance hole at the crossover has a drop structure built into the invert to eliminate or reduce turbulence in the line. The contractor used a series of two Godwin Pumps to maintain the flow of the sanitary sewage as construction proceeded between maintenance holes.

Engineers redesigned the maintenance hole at Commissioners Road and Gordon Avenue so that the benching directs the inflow to the outflow at a wider angle, thereby significantly reducing the opportunity for turbulence of the sewage to occur. The maintenance hole is also lined to enhance the performance of the structure.

The final phase of the project may be the construction of a biofilter to pull any H2S gas from the air in the sewer. The City has decided to monitor gas emissions in the new line to determine if a biofilter is necessary.

The $1.7 million contract began in late April and concluded by the end of July 2004.


Neil Wyatt is with Hanson Pipe & Products Canada, Inc., Cambridge, Ontario.
Contact e-mail: neil.wyatt@hansonamerica.com

See our home page on how to order your subscription. We regret we can only accept orders from Canada.