Environmental Science & Engineering - www.esemag.com - March 2005
Comments? send them to the editor.

Huge York-Peel feedermain spurs construction of hi-tech pressure pipe plant

By Jim Tully, Munro Concrete Products

Manufacture of steel cylinders for lined and embedded cylinder pressure pipe.
Few know that Canadian and Austrian engineering ingenuity was behind one of the largest watermain projects in the Greater Toronto Area (GTA). In record time, a new pressure pipe plant was constructed in Barrie, Ontario, to supply product to the $104-million York- Peel Feedermain that will transport up to 381 million litres of treated water per day from Peel Region to neighbouring York Region. The plant is the largest pressure pipe plant producing small and large diameter precast concrete pressure pipe under one roof in North America.

Immediately following the award of two separate contracts for the York-Peel Feedermain to Dufferin Construction Company in July 2003, engineers at Munro Concrete Products began a fasttrack design and construction project to meet the scheduling demands of the Dufferin design-build team assembled to construct the feedermain. Already recognized as a pioneer in fully robotic concrete pipe production, Munro teamed with its equipment supplier, Schlüsselbauer Technology GmbH & Co. KG of Gaspoltshofen, Austria, to build Canada’s premier automated concrete pressure pipe plant. Since design of pressure pipe plants had not changed much over the past 30 years, Munro saw this project as a one-time opportunity to advance the technology for producing pressure pipe.

To meet a sharp rise in demand for treated water in the GTA, Peel and York Region negotiated a unique arrangement to build infrastructure to provide water for York. Until the feedermain was constructed, York’s major urban areas received drinking water from The City of Toronto, Lake Simcoe (north of Toronto), and wells. Peel draws its water from Lake Ontario and treats it lakeside before it is pumped to reservoirs.

The $72 million design-build contract for York Region was the first portion of the project that was awarded. This section of the 1800 mm diameter (72-inch) feedermain and associated road works, running 13 kilometres from the York-Peel boundary at Highway 50 to the Maple Reservoir in Vaughan, is one of several projects that compromise the Water and Sewer York-Peel Agreement signed in February 2002. When the entire system is complete, additional water conveyance of 40 ML per day will be delivered to York Region.

The $32 million design-build contract for the Region of Peel is the second portion of the project that was awarded. This 8-kilometre section involves the design and construction of a 2100 mm (84-inch) diameter concrete pressure pipe along Airport Road in Brampton from Queen Street to the new Airport Road Pumping Station and Reservoir and an 1800 mm diameter feedermain from the Airport Road Pumping station along Castlemore Road to the Peel-York boundary at Highway 50, where it joins up with the York Region contract.

Dufferin Construction Company of Oakville is overseeing the design-build of the 21-kilometre transmission line and associated road and civil engineering works. Consultants include Earth Tech Canada, Marshall Macklin Monaghan, URS Canada and John Emery Geotechnical Engineering Ltd. Six 10-member crews worked simultaneously on the project at peak construction periods, installing pipe along various sections of the two contracts. The feedermain design portion of the project is jointly managed by Joe Sframeli of Marshall Macklin Monaghan and John Bourrie of Earth Tech Canada. Larry Lorusso is the senior project manager from Dufferin Construction Company, a division of St. Lawrence Cement Inc.

While Dufferin’s consultants were preparing the necessary engineering plans and reports for construction of the Peel and York contracts, Munro’s engineers met with counterparts at Ellis Don and Schlüsselbauer to design the plant around a custom-built semi-robotic production facility. In little more than 45 days, Munro and its partners had designed the plant and decided on the equipment suppliers. By August 18, 2003, the necessary approvals had been secured and construction of the new plant was underway. Five months later on January 23, 2004, the first pressure pipe was produced. By February 19, 2004, the plant was in full production.

Hydrostatic testing of steel cylinders.
The 8,550 square metres (92,000 square foot) plant features a Schlüsselbauer core casting station and pipe tipper. The pipe tipper is unique as traditional pressure pipe plants use cranes to adjust the pipe from a vertical to a horizontal aspect. The Austrian firm acted as agent to secure additional process machines that interconnect with its technology. These included a wire prestressing machine, hydrostatic testing equipment for the steel cylinders which make the pipe water tight, spiral welder, and equipment to form the steel cylinders.

The moulds for the core casting station are also Schlüsselbauer products capable of producing pipe sizes from 400 mm to 3000 mm inside diameter, with a standard length of 6,096 mm (20 feet). The large 1800 mm and 2100 mm diameter moulds are the first moulds used in the new casting station. Hydraulically-activated mould jackets expand with the push of a button and the core collapses, so that the precast pressure pipe casting can be lifted and moved to a curing chamber. The moulds can be reused every 6 hours, producing 4 units of pipe in 24 hours from a single mould.

The plant is designed to produce both lined and embedded cylinder pipe. Pressure pipe, 1500 mm diameter and smaller, is lined cylinder pipe, and pipe 1650 mm diameter and larger is embedded. Embedded and lined cylinder pipe is produced to specification American Water Works Association (AWWA) C301 Prestressed Concrete Pressure Pipe, Steel Cylinder Type, for Water and Other Liquids. With embedded cylinder pressure pipe, concrete is poured on the inside and outside of the cylinder surface. Once cured, the concrete pipe surface is wrapped with prestressed wire that is then coated with mortar. Lined cylinder pipe has concrete poured on the inside of the steel cylinder which is then wrapped with prestressed wire directly on the surface of the steel cylinder. The wire and cylinder are then coated with mortar to protect the prestressed wire.

AWWA C301 requires the freshlycast core to cure for 12 hours. A serial number is stamped on the end ring of every pipe to track it through production and installation. After curing, the pipe is rotated to a horizontal position and then wrapped with the prestressed wire. After coating with mortar, the pipe is once again placed in a curing chamber for 12 hours.

The plant has been designed on the back of experience with the fully robotic Schlüsselbauer Exact 2500 gravity pipe plant also located at Munro. The versatility of the new pressure pipe plant can accommodate the production of smaller diameter lined cylinder pipe using the packerhead method. The plant is now capable of producing 400 mm diameter to 3000 mm diameter pressure pipe to serve a Canadian and NE/ Midwest USA marketplace.

In addition to the precision product being produced from the Munro facility, the local economy is also getting a boost from the construction and maintenance of the facility itself, and the many plant jobs that were created by the construction of the feedermain.


Jim Tully, P.Eng., is with Munro Concrete Products, Barrie, Ontario.
Contact email: jim.tully@munroconcrete.com.


See our home page on how to order your subscription. We regret we can only accept orders from Canada.