![]() |
| Exposing existing utilities
|
![]() |
| Pipe being pulled back
|
Currently there are many highly qualified contractors that perform Open Cut installation of sewers; however, there are fewer contractors capable of Horizontal Directional Drilling (HDD) of sewers. Site constraints often dictate which method of sewer installation is specified – for example, the size or slope or geotechnical conditions may dictate one method over the other. But what happens in cases where both construction methods are appropriate? Does the designer specify what they believe is the most appropriate method? Is it appropriate to limit a tender to one method of construction or should both methods be tendered? Can both construction methods be tendered and evaluated fairly?
A recent tender for the construction of a 300 m long 250 mm diameter sanitary sewer on Leslie Street, north of Eglinton Avenue, in the City of Toronto helped tackle these questions. The sewer was required for the Carrington Condominium, being developed by Monarch Construction Limited.
Design
In order to consider the feasibility of HDD, the following items needed to be confirmed:
As with most municipal infrastructure, the Public Works Department of the municipality sets the standards on what is permitted. Early on in this project the City of Toronto was approached to determine if they would be receptive to the use of HDD and high density polyethylene pipe for the installation of the sewer. HDD was considered to have merits on this project, as the sewer was located at the centre of a busy five-lane arterial road. The City was receptive to the use of this technique at this site, provided appropriate measures were incorporated.
Appropriate measures were developed and agreed upon with the City to ensure adequate control of the horizontal and vertical alignment. The following controls were developed for approval by the City:
Horizontal Control – standard location in road with a curvilinear alignment and a horizontal deviation of up to one pipe diameter.
Vertical Control – maximum depth of cover of 4.0 m with positive grade of 1% minimum (design grade) throughout. The widespread use of CCTV for sewer inspection played a role in the City agreeing to these conditions.
A geotechnical investigation was undertaken and comments specific to both open cut and directional drilling were provided. The prevailing geotechnical conditions did not eliminate HDD as an option; however, the geotechnical report cautioned that the possible presence of stones and boulders might hamper progress. Utilities and municipal services along the sewer alignment were located in the plan and their depths were approximated to confirm that there were appropriate alignments available for HDD.
After addressing these issues, it was determined that this sewer was a candidate for the HDD construction technique.
Tendering
Both the conventional open cut and the HDD portion of the tender contained the typical tender items. An additional item was included that required the bidders to indicate the total asphalt removal area needed for their method of construction. The unit cost for permanent asphalt restoration, as provided by the City, was indicated in the contract. The permanent asphalt restoration cost was indicated in the tender as being a factor that would be considered in the evaluation of the bids. The lower the total asphalt removal area indicated by the bidder, the lower the permanent restoration cost would be. This was to the advantage of the bidders using HDD and narrow trenches. The tender also indicated that exceeding the total asphalt removal area would result in a backcharge to the contractor. This approach leveled the playing field by considering restoration costs as part of the tender evaluation, to arrive at a total project construction cost.
To the advantage of the open cut bidders, the HDD portion of the tender included two additional items for a detailed HDD work plan, and for exposing all utilities to confirm their elevations. HDD contractors often expose utilities and municipal services to help plan the bore and confirm clearances. To the advantage of the HDD bidders, one manhole was eliminated due to the City permitting a curvilinear alignment when using HDD.
All of these factors were known by the contractors during the tendering process, allowing the contractors the opportunity to make strategic decisions prior to submitting their bids.
![]() |
| Set-up near busy intersection
|
After comparing apples to apples, the lowest total project construction cost was realized by the HDD method and the contract was awarded to A.Van Egmond Construction Limited.
For this project the percentage cost savings was determined by comparing the average price of the three low bids for each construction method. A savings of 40% without considering restoration, and a savings of 46% when considering restoration, was achieved with HDD. We believe a significant portion of this savings was through the reduction in the quantity of nonshrinkable fill required with the HDD method. These savings should not be considered as typical, as the successful method and the cost savings will vary with site-specific conditions and market conditions. However, this demonstrates that there are savings that can be achieved when both construction methods are tendered.
Construction Issues
The continuous pipe through the manhole may have some hydraulic advantages. It is also possible to remove the pipe through the manhole; however, there does not appear to be any advantage in doing this.
Drop structures are typically done with the same material as the mainline pipe. For example, an open cut sanitary sewer constructed of PVC would typically use pre-manufactured PVC fittings for the drop structure. With HDPE pipe the same selection of fittings is not readily available. On this project a PVC drop structure was used, requiring a coupler fitting to adapt between the HDPE and the PVC pipe, prior to the drop structure.
These deviations from the municipal standards were rather minor; however, as HDD increases in availability and popularity, we expect that the required standards will be developed.
Conclusion
The selection of the appropriate method of construction is often determined
by site conditions; however, where site conditions permit both open cut
and HDD, consideration should be given to tendering both alternatives.
It is prudent to outline the tender evaluation criteria to ensure there
will be a fair comparison of the two methods.
|
|
See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.