Environmental Science & Engineering - www.esemag.com - May 2005
Comments? send them to the editor.

Innovative system keeps Toronto cool


Protected valve assembly ready for installation.
By using cold water from Lake Ontario, Toronto’s Deep Lake Water Cooling Project is capable of cooling 20 million square feet of office space (100 high rise towers). The project, which began operating late last year, is expected to reduce annual carbon dioxide emissions by 40,000 tons and energy use by up to 75% less than conventional electric chillers. (An article on this project appeared in ES&E’s September 2003 issue. Visit www.esemag.com)

There is an additional benefit to this project. Spent water from the cooling phase is passed through a cold-energy transfer loop back into one of the city’s filtration plants to produce cooler potable drinking water.

Initially, cold water is drawn through three parallel, 600 mm HDPE intake pipes from a depth of 85 metres, 5.6 kilometres south of the city, out in Lake Ontario. These pipes are buried where water depth does not exceed 10 metres, in order to protect them from damage from large wave and current loads, as well as marine traffic and anchors.

Where water depth is greater than 10 metres, the pipe is laid on the lake bottom. Screens are provided at the intake to prevent fish and other organisms from entering.

Water is passed through a heat exchanger at a temperature of 4.7 degrees Celsius and exits at a temperature of 12.5 degrees Celsius, traveling through the city’s municipal water distribution system. Return water enters the exchanger at a temperature of 13.1 degrees Celsius and, by adding more cold, fresh lake water, the temperature is brought down to 5.0 degrees Celsius. From here, it is pumped through 1200 mm diameter pipes to an underground facility in the downtown core. From this underground chamber, it will be further chilled to 3.3 degrees Celsius and distributed to office and residential towers for air-conditioning circuits.

Corrosion protection tape products must withstand such cold temperatures and still be flexible enough to be applied to metal pipes and fittings while in operation. The tape must also show all the attributes of petrolatum tapes and provide long-term corrosion protection and sealing. Products selected for this massive and innovative project were Denso LT tape, Paste and Mastic.

The application involved assembling 1200 mm flanged joints, which connected two steel pipe sections complete with a valve assembly. The sections were built on their ends, off site. When assembled they stood about eight feet tall. The application of Denso Paste went around the nut and bolt assemblies and the pipe sections along with a large amount of Profiling Mastic to fill the many voids. Irregular configurations on this section highlighted the tape’s conformability.

Once completed, the concrete lined assemblies, now weighing several tons, had to be moved by crane onto a truck and then transported to the job site 60 km away. Once on site, the assemblies were lowered about 80 ft below the road surface down to a tunnel, which had been bored using a huge vertical drilling machine. The tunnel runs from Lake Ontario, where the large diameter water pipes were then connected with the assemblies to the piping that runs underneath the city. Once the large diameter piping was protected and connected, the small diameter feeder pipes and valves that connect to various office buildings were protected with the Denso Petrolatum System.


Contact: sales@densona.com.

See our home page on how to order your subscription. We regret we can only accept orders from Canada.