Environmental Science & Engineering - www.esemag.com - May 2005
Comments? send them to the editor.
Hi-tech project defends the Riviera
 |
| Philippe Porcu
|
For most, Monaco means glitz
and glamour, racing cars and
casinos. But aside from its reputation
as a destination for the
international jet set, the principality is
an extremely dynamic state, with
32,000 inhabitants and a busy port
which has recently been expanded.
One of the world’s smallest states,
Monaco is installing the largest watertight
container ever built.
“The government under the impetus
of HRH The Sovereign Prince decided
to construct a new barrage in order to
enlarge the Hercules Port. This will
provide it with new infrastructure and
protect the harbour from the strong
east winds,” explains Philippe Porcu,
assistant technical director for the sanitation
division at the SDAU, Monaco’s
urban development service. “The sea
is very deep in the harbour with
extremely thick silt, making a traditional
solution impossible, so we came
up with the idea of a semi-floating barrage
along with a more traditional
counter pier,” he explains.
The barrage weighs in at 160,000
tonnes and was delivered in August
2002. It measures a massive 352
metres long, 28 metres wide and 19
metres deep, and was constructed over
three years at Algeciras in Spain and
towed 1,500 kilometres to its final
position by ship, a sea voyage that took
almost two weeks. In addition to providing
a breakwater, the barrage also
contains a four-level “underground”
car park, dry dock, two passenger terminals
and other commercial and
administration premises.
“The barrage is anchored to terra
firma using a kind of ball and socket,
weighing 700 tonnes, which allows the
pier to move while remaining
attached,” Mr. Porcu explains. “At its
tip, it can move up to 15 metres laterally
and around 1.30 metres up and
down. The construction is also held to
the sea floor by anchors. The counter
pier stands firm on pillars on the other
side of the port.
“The port is on the same level as
Monaco's purification plant; previously,
water from both boats and the port
couldn't be evacuated using gravity, and
it was necessary to bring in trucks to
pump their waste,” he explains. “But the
barrage and harbour are equipped with
pumping units that enable all wastewater
from the barrier, from ships berthed
there and from those permanently
moored in the port to be sent for treatment.
This is very significant in terms of
protecting the environment - our main
goal. Previously, ships disposed of
everything at sea, but now we can treat
all the effluent as well as rainwater and
run-off, thanks to the hydrocarbon separators
we've installed,” he explains.
A series of underground service
tunnels have also been constructed to
carry wastewater, drinking water, electrical
and telephone cables. Because
they are situated below sea level, these
galleries are also equipped with special pumps to remove any leaked water.
These pumps are equipped with
“skirts” to lower the evacuation level
to just 1.5 centimetres from the floor.
In addition, the entire network has
been equipped with a remote surveillance
system. “Now we can monitor
any potential problem with the pumps,
stations or separators, and deal with any
situations that may arise as rapidly as
possible,” Mr. Porcu explains. “We can
also monitor flow rates and water levels
and are able to operate various valves
remotely to optimise the functioning of
the principality’s whole sanitation network,
which also handles effluent from
the neighbouring districts.”
Pierre-Louis Odouard is project
manager for Somoclim, the Monacobased
firm responsible for installing
the pumps on the Monte Carlo port
network. “This installation was a real
challenge, in terms of both setting up
the operation as well as the materials
used,” he says. “Because the networks
and stations are below sea level, we
had to construct ballasts around the
pump stations, and the installation had
to be done by divers. Other constraints
meant we had to use special materials.
The pumps are industrial seawater
models, with an epoxy coating,
equipped with anodes. The prefabricated
units are made of reinforced polyester
with stainless steel parts, and all
piping is polyethylene.”
When the project is finished in
2008, the whole port will have been
entirely redeveloped and its facilities
doubled. It will provide berthing to
large yachts and cruise ships; new jetties
and commercial premises are
planned as well as the restructuring of
the north and south harbour basins.
Anatomy of a barrage
The semi-floating barrage contains:
- Ten Flygt CP 3057 HT 250 2.4 kW
pumps, two units per hydrocarbon separator
in the car park and dry dock
inside the barrage.
- Two industrial-version seawater CP
3127 MT 430 5.9 kW pumps for a rainwater
separator that can take seawater.
- Five BS 2060 MT 232 for evacuating
any infiltrated water.
The counter pier contains:
- One TOP 80 station equipped with
two industrial and seawater version CP
3102 HT 252 pumps for rainwater collection.
- Two SPM 1251 sewage stations,
each twinned with an industrial and
seawater-version CP 3127 HT 480
with flush valve for pumping wastewater
from moored craft.
- One TOP 100 station equipped with
two industrial-version seawater CP
3085 MT 434 pumps to collect wastewater
from buildings on the quayside
and pleasure craft.
On land, there is:
- One station SPM 3001 equipped
with three industrial-version CP 3201
HT 456 30 kW for transferring waste-
water from cruise ships.
- The stations on the counter pier and
the port are regulated using FMC 200
and 300.
This technology was recognized as
“Best Real-Estate Project” by the Jury
at Barcelona Meeting Point 2002, and
won a Leonard Award at the Immotech
show 2004 in Geneva.
Contact ITT Flygt: email fcdn.info@itt.com,
or visit www.itt.flygt.ca.
See our home page on how to order your subscription. We regret we can
only accept orders from Canada.