Designing a multi-purpose pumping and storage facility
Finished main pump room.
The Airport Road Reservoir and
Pumping Station project was
designed to supply enough
water storage and pumping
capacity to serve both the Regional
Municipality of Peel and the Regional
Municipality of York’s future water
demand needs. These huge Ontario
regions both have rapidly increasing
populations.
The pumping station was proposed
to pump to three separate pressure districts,
Peel 4E, Peel 5E, and York. The
facility was designed to provide adequate
and safe drinking water to both
municipalities’ residents, in a costeffective
and timely manner. The
client’s objective was to design a reservoir
and pumping station that could
meet the supply needs for the receiving
water systems for projected flows in
the year 2011 (Phase I), but also have
the capability of upgrading the capacity
to meet the ultimate design flows
projected for the year 2036 (Phase II).
The client also had more specific
objectives for the design of the pumping
station itself. A hydraulic transient
analysis was conducted on the entire
water system, from the incoming water
supply to the outgoing discharge pressure
zones. This analysis looked into
potential hydraulic transient issues,
proposed surge control schematics,
and proposed pump and valve operation.
The pumping station included a
surge protection system to minimize
the impacts of potentially destructive
forces due to high and low pressures in
the discharge pipes. Emergency power
was also included in the design to
ensure the pumping station could continue
to supply water in the event of
power failures.
MacViro’s solution to the storage
and pumping capacity needed to meet
the future demands was to design a
52.5 megalitre reservoir footprint to
supply the pumping station with an
uninterrupted water supply. The reservoir
was designed to meet the Phase II
flows of 633 ML/d, but was only constructed
to meet the design flows for
Phase I of 316 ML/d. This resulted in
the construction of two out of the three
reservoir cells totaling 35 ML.
The pumping station was designed
in a similar fashion to meet the pumping
requirements for Phase II, but only
constructed to meet the design flow for
Phase I. The pumping station design is
essentially three separate pumping stations
housed under the same roof. This
design costs much less than building
three separate stations, since many
components required to run a pumping
station can be used by all three systems.
There are three sets of pumps
individually sized to meet the demands
of the three individual pumping zones.
All of the pumps share a common
reservoir, suction is through two separate
1800 mm suction headers, and discharge
is through three individual discharge
headers (1800 mm, 1500 mm,
and 900 mm).
Installation of piping and equipment in the main pump room.
Matching the pump motor drive
efficiencies and large hydraulic head
variations required variable frequency
drives (VFD) to be installed. Pump
selection and operation will be based
on obtaining the best efficiencies and
having gradual changes in flow to
match the demand for York and Peel
4E. The Owner’s recognition of the
operational flexibility advantages for
this approach resulted in the addition
of a VFD for Peel 5E.
The pumping system is protected
from high surge pressures, due to
power failure, in two ways. Lower
pressure Peel systems (4E and 5E) are
protected from high surge pressures by
using four surge anticipating valves,
two on each system. The York system,
which has significantly higher surge
pressures, is protected by using two
225m3 surge tanks. These tanks act as an air cushion to dissipate high water
pressures and minimize downsurge
effects in the pipelines.
Two 1825 KW diesel generators
provide emergency power to the station
in case of a power failure. The
generators supply power to all essential
equipment needed to run the
pumping station. The generators were
sized to provide power to run only two
pumps on each pumping system.
Two chemical disinfection systems
were designed to disinfect the water
both coming into the reservoir and
leaving the pumping station. A chlorine
injection system with 16,000 L of
storage for Phase I was designed to
deliver chlorine, in the form of sodium
hypochlorite, to the inlet of the reservoir
and the discharge of the Peel 4E,
Peel 5E, and York systems. An ammonia
injection system with 16,000 L of
storage for Phase I was designed to
deliver ammonia to the York system
only. This provides chlorine and
ammonia in the York system, which
combine to form chloramines for
maintenance of a chloramine residual
in the distribution system.
The station’s design allows for
future expansion and installation of
equipment to meet the Phase II design
flows. Connection points and extra
room were included to allow for the
additional pumps, valves, piping, generators,
chemical storage, and reservoir
storage required for Phase II.
The communities that are being
supplied by the Airport Road Pumping
Station are rapidly growing, as are
their water demands. Communities to
the north, in both municipalities, rely
heavily on well water. As the population
grows, these wells will not be able
to keep up with the demand. The
Airport Road Pumping Station will
start to supply communities that were
originally on well water. This will
allow the Yonge St. aquifer and the
Oak Ridges Moraine watershed
abstractions to be reduced.
Technical excellence and
innovation
The use of an 800 tonne hydraulic
crane, one of three in Canada, to drop
equipment into the buildings saved
months of inactive building time.
Since the construction started in
September 2003, there was a need to
pour concrete foundations and erect
building walls before the winter
months would slow construction. It
was decided to completely erect the
pumping station walls before installing
any equipment. Since much of the
equipment was too large to fit through
the pumping station service bay doors,
and maneuver in place, the hydraulic
crane allowed the equipment to be
dropped into the pumping station
through the roof opening.
In order to design an efficient and
safe pumping station, a hydraulic transient
analysis was used to model the
proposed pumping station’s operation.
The transient analysis was used to
ensure that potential hydraulic transient
issues pertaining to the environment,
public health and safety, infrastructure
risk management, energy
efficiency and optimal pumping operation
were identified and addressed.
These issues included:
Sub-atmospheric pressure upon
pump shut-down can induce groundwater
intrusion and air entrainment
resulting in public health and safety
issues.
Pipe or pump break can occur due to the high transient pressure upon vacuum/
air pockets collapsing or flow
reversal back to the Airport Road
Pumping Station.
The magnitude, frequency and duration
of the pressure spikes may cause
pipe material fatigue and loose
anchors, resulting in an infrastructure
risk management concern.
Other objectives of the hydraulic
transient analysis were to develop a
surge control scheme that would protect
the pumping station and the discharge
feedermains from the high and
low pressures induced by the emergency
pump shut-down and start-up. It
also outlined pump and valve operation
procedures to provide efficient
operation, while minimizing pressure
surges related to starting and stopping
equipment.
With regards to the low water level
and suction conditions, the design of
the reservoir was unique. It was
designed to allow the reservoir to be
drained down to almost entirely empty.
The recessed suction lines allow the
reservoir low water level to be set at
the reservoir floor elevation. A typical
reservoir would only allow the water
level to drop to a few metres above the
floor level before adverse conditions
around the suction lines would occur.
Since the Airport Road Reservoir can
be lowered to essentially empty it takes
advantage of the entire reservoir
capacity.
Level of complexity
One of the most important obstacles
to be overcome was the time constraint
on the entire project. A reservoir
and pumping station of this size
would typically require three years to
plan, design, and construct. The timeframe
from the initial planning stages
to final construction of the Airport
Road Reservoir and Pumping Station
was a mere one and a half years. Much
of the design of the pumping station
took place while construction of the
reservoir and pumping building was in
progress. An initial design was implemented
and the construction started.
Final design details were attended to
during construction.
This reservoir and pumping station
are complex compared to other more
typical pumping stations. The complexity
is due to the fact that one
pumping station must pump to three
separate systems. The station was simplified
by housing all three systems in
the same building and allowing them
to share common resources (chemicals,
emergency power, water supply)
but they must be independently controlled
by separate interfaces. Control
sequences and programming for three
separate pumping systems were provided.
They all use common resources.
Hydraulic transient analyses were
complex to perform due to the unique
design of the pumping station and the
three discharge pressure zones. Under
normal circumstances, the transient
analysis would be simple and straightforward,
using just one discharge and
one pressure zone. The Airport Road
Pumping Station analysis needed to
take into consideration three pressure
zones consisting of over 19 pumping
stations and reservoirs, and all of the
interconnecting piping.
The inlet structure of the reservoir is
a very unique design. The incoming
water supply conditions posed a design
problem, since the Airport Road
Reservoir was at the same elevation as
the incoming water line. Water needed to
be pumped to a high point and allowed to
flow by gravity to the reservoir.
If the reservoir water level was very
low, the incoming water line could
possibly run dry, due to gravity emptying
the pipeline. This condition would
pose a water quality issue, and “repriming”
of the pipeline would be
needed. To avoid this potential problem,
the reservoir inlet structure was
designed to keep the incoming pipeline
flooded and pressurized to maintain
water quality. The 16 metre high inlet
structure provides 16 metres of head
inside of the incoming pipeline. The
height of the inlet structure water level
can be regulated through three electrically
operated weir gates.
The level of redundancy for the suction
headers requested by the client
added to the complexity of the facility.
The client wanted to have the ability to
continue pumping even if a suction
header had to be taken out of service.
For this reason, two suction headers
were designed to take water from alternating
reservoir cells.
Conclusion
The new facility will achieve sustainability
of our natural resources by
reducing the demand for water on the
natural aquifers and water tables, and
by reducing the number of households
that rely on groundwater. The pumping
station and reservoir were strategically
located in an area that would not pose
any negative impacts on agriculture,
hydrology, landforms, soils, or fisheries.
An Environmental Assessment
Report for the York/Peel feedermain
and an Environmental Study Report
for the Northeast Brampton Water
Supply were conducted to ensure that
environmental principles were followed.
The location was chosen to
minimize environmental impacts,
based on the findings of the two
reports. Feedermains leaving the
pumping station were mainly constructed
on road right-of-ways and
through existing pipeline corridors to
avoid any environmentally sensitive
areas.
The emergency power system has
been equipped with load monitoring
and peak shaving capabilities to
become a Provincial Smart Energy
plant. The Airport Road Pumping
Station can monitor power consumption
levels on the power grid and start
the diesel generators to reduce the
power consumption of the pumping
station during high demand periods.
The current diesel generators are also
capable of bi/fuel power generation
using natural gas. This capability for
use of the generator with natural gas
will also allow for reduced air emissions.