Environmental Science & Engineering - www.esemag.com - June 2003
Comments? send them to the editor.

New drainage project improves water quality of international waterway

By Robin Woodbury,
Premarc Corporation,Michigan

Lake St. Clair’s Metropolitan Beach in Macomb County, Michigan was closed most of the summer of 1994 due to persistent readings of high levels of Escherichia Coliform (E. Coli). Although the cause of the E. Coli was not conclusively identified, it had been alleged that some of this pollution could be attributed to Combined Sewer Overflow (CSO) coming from the Red Run Drain.

The Federal Clean Water Act of 1977 mandates that all discharges of pollutants into the waters of the United States must be authorized by a National Pollutant Discharge Elimination System (NPDES) permit. The Southeastern Oakland County Sewer District System (SOCSDS) Twelve Towns Retention/Treatment Facility (RTF) was originally authorized to discharge treated combined sewer overflows (CSOs) into the Red Run Drain, a tributary of the Clinton River that flows to Lake St. Clair, an international waterway. This 2.2 mile-long RTF was one of the first CSO control projects constructed in the US. When completed in 1973, it was considered stateof- the-art.

Time, however, revealed many deficiencies. While the storage volume of the facility approaches the standards now accepted by the Michigan Department of Environmental Quality (MDEQ), the configuration was insufficient to protect the environment. Rainfall events that exceed 1/2 to 3/4 inches in depth can generate large overflow volumes. Due to the mixing of sanitary and storm water, this discharge is inevitably contaminated with human, commercial and industrial wastes. The CSOs that are discharged from the Twelve Towns RTF were thought to have contributed to the high levels of E. Coli found at Metropolitan Beach.

Political pressure to address these deficiencies led to a solution known as the George W. Kuhn Drainage Improvements Projects. Through the cooperative effort between the Oakland County Drain Commissioner and the 14 communities that now make up the George W. Kuhn Drainage District, a mutually agreeable program was developed to upgrade the RTF to improve the water quality of the Clinton River and Lake St. Clair.

Contract One of the new drainage improvement project dealt specifically with removing and rerouting storm water inflow from the Twelve Towns RTF, thus reducing the frequency of overflow of sewage to the Red Run Drain. The new system was designed to intercept existing combined flows from a 60-inch and 72-inch line that previously discharged directly into the retention treatment facility without benefit of pre-treatment. The new system rerouted flow to a point upstream for future connection to the treatment facility proposed as a part of Contract Four.

Construction of Contract One, started in October of 2000, was completed in July of 2002. The project consisted of the installation of two new storm drains that run parallel to the RTF. These two parallel drains are known as the North Drain and South Drain.

Construction of the North Drain included installation of approximately 9,600 linear feet of main line pipe ranging in size from 78-inch to 126- inch diameter reinforced concrete pipe (RCP). Construction of the South Drain included approximately 8,100 linear feet ranging in size from 66-inch to 126-inch diameter RCP.

Numerous impediments were encountered during construction of the new drains. Additional time and energy was spent snaking the pipe around utilities so that services were not disrupted. To limit impact on local traffic, construction through the road crossings was performed during weekends.

Coordination of construction activities was crucial around a recreation facility known as the Red Oaks Wave Pool. While the North Drain followed the property line of the wave pool complex, the South Drain went directly through the facility’s parking lots. Work on this portion of the project was completed during fall and winter to ensure the opening of the complex in the spring.

Due to lack of space, and fear of damaging the existing RTF, soils from the excavation of the new storm lines could not be placed on or near the RTF. A solution to the temporary storage and disposal of excavated soils was found at the Red Oaks Golf Course where construction was to proceed through the facility. When the newly restored Red Oaks Golf Course opens in the spring of 2004, golfers will face a new and more challenging course constructed with the spoils of the Kuhn Drainage Improvements Projects.

Public concern arose, however, over the soils that were being excavated since a portion of the golf course covered an area that was once used as a landfill and incinerator. In conjunction with the MDEQ, the Oakland County Drain Office, held numerous public meetings informing and educating the public on the monitoring and dust suppression programs which were in use during this portion of the project.

Forty-two major storm drains were disconnected from the RTF and reconnected to the North and South Drains. Storms and flooding of the construction site were a major concern for the contractor, so a warning system was established that sounded an alarm when rainstorms were approaching. This allowed time to get people out of the RTF before the storm.

Improvements to the Twelve Towns RTF included 15 projects under five separate contracts. All of the projects were incorporated into the facility’s NPDES permit. The estimated project cost for these 15 projects is nearly $144 million (US).

See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.