Environmental Science & Engineering - www.esemag.com - July 2005
Comments? send them to the editor.

Innovative reinforced concrete pipe drop structure used to construct stormwater outfall

By Albert Wissa and Kent Campbell

Assembly of a standard 1200 mm diameter maintenance hole from the transition structure to the surface.
Development of tableland, north of Sheppard Avenue and east of Meadowvale Road in the Scarborough Community Council Area of the City of Toronto, has been planned for residential use for decades. A major concern addressed throughout the planning process has always been the fragile nature of the steep bluffs dropping sharply to the Rouge River. Closely associated with the nature of the bluffs is the sensitivity of the river and valley ecosystem to the impacts of development.

Environmental studies and reports detailed the constraints to be imposed on any development of the tableland to protect the Rouge River Valley and all of its elements. Proactive citizens and local residents organized to be sure that environmental issues were addressed throughout the development application process, and solutions to mitigate potential environmental damage were thoroughly reviewed before approvals for construction were granted.

Mattamy (Rouge) Limited was one of the development applications that required approvals to discharge stormwater from its site to the Rouge River. A stormwater management pond had to be constructed on the tableland, outside of a 30-metre buffer from the edge of the steep slope to the river. A storm sewer outfall at the base of the steep valley slope was constructed by trenchless technology so that the impact of the outfall within the valley was limited to the headwall and approximately 50 metres of stonelined open channel to the river.

Stormwater is now collected from the housing development in a network of storm sewers and discharged into a stormwater management pond. From there, the water drains to a 975 mm diameter concrete pipe outlet and is conveyed by a 31.3-metre deep drop structure (900 mm diameter) to the base of the slope. At this point, the flow is directed from a specially engineered energy dissipater box, through a jacked 1200 mm diameter concrete pipe to the Rouge River. By the time the stormwater reaches the river, its velocity is minimized to prevent any erosion of the riverbanks.

Niran Construction of Toronto was awarded the contract for sewer and watermain services. The contractor immediately proposed an alternative to the design of the drop structure that would comprise a system of precast concrete maintenance hole components readily available from Hanson Pipe & Products Canada, Inc. of Cambridge. Using a precast concrete system of standard gravity pipe, jacking pipe, and maintenance holes would result in the least impact on the environment and construction cost savings to the client.

The concept for the drop structure included the following major elements: Niran commenced excavation of the 4600 mm diameter working shaft in mid February, 2004. The silty clay till did not present any major obstacle to construction and there was very little groundwater seepage.

The process for the dig involved an open pit excavation of about 1.0 to 1.5 metres per day. A steel liner plate was constructed each day as the pit progressed. The first section of liner was about 4 metres deep with one metre raised above ground level to provide a safety barrier for workers and any visitors to site. At one point in the dig, small amounts of explosives were required to loosen the soil. A Bobcat was lowered into the shaft and used for excavating the earth. Once the invert elevation of the shaft was reached, the Bobcat was removed and replaced with tunnel jacking equipment.

Throughout the dig, all safety precautions were taken including the use of fans for ventilation, ladders, safety platforms, and lighting.

Tunnel outfall to channel: Outfall to Rouge River using jacked 1200 mm diameter reinforced concrete pipe.
The shaft was required so that 95.5 metres of 1200 mm diameter jacking pipe could be jacked from the 3000 mm diameter maintenance hole riser at the base of the drop structure. The jacked pipe connects to the maintenance hole by means of a “doghoused” opening in the first 3000 mm riser at the base of the shaft to provide an outlet to the creek. An internal granite box was specially designed by Niran to accommodate the velocity and weight of freefalling stormwater and dissipate its energy. Once the outfall pipe had been jacked into position and the 3000 mm diameter riser installed, the base of the drop structure was ready for construction of the 2400 mm x 1200 mm maintenance shaft that contained the 900 mm diameter concrete drop structure.

The idea for the internal drop structure came from Hanson’s engineers. There was some concern that an external concrete drop structure might shift and crack. In addition, an external drop structure (concrete or PVC) would have required a steel lined working shaft to accommodate pipe and equipment. The construction cost could have been much higher. With an internal drop, the concern about cracks in the concrete drop structure was alleviated and the cost of construction reduced dramatically.

Construction of the maintenance shaft and drop structure took two weeks as all components were precast concrete maintenance hole components. Only two pieces per day were permitted to be installed since the space between the precast concrete structure and the metal-lined wall of the shaft was filled with non-shrink fill, as work progressed. Engineers required proper time for the fill to set.

The entire shaft is made accessible by a combination of aluminum safety platforms and steps built into the risers at the Hanson plant. Design engineer for this structure was Dave Grahlman of Gamsby and Mannerow Limited.

When work reached the elevation where the inlet pipe from the pond entered the vertical drop shaft, a special transition structure comprised of a weir and benching was specially designed by the Hanson engineering team. The challenge was to provide benching that did not cause turbulence of the stormwater as it entered the structure, and reduced the entrant coefficient for the flow transitioning from the 975 mm horizontal pipe to the 900 mm vertical pipe. Hanson engineers used a unit of elliptical pipe with convex benching at the base as a reducer to direct the flow into the drop shaft. The reducer was placed between the outlet of the 975 mm concrete pipe extending from the stormwater management pond and a 2400 mm x 1200 mm riser constructed with a 200 mm wide weir (designed for a 100-year storm event) that prevents normal flows from the pond from entering the maintenance access shaft that parallels the length of the drop structure.

Once the transition structure including reducer and weir were in place, the contractor was able to continue with the construction of a standard 1200 mm diameter maintenance hole to the surface.

Jacking the outfall pipe from the structure at the bottom of the shaft, and construction of the headwall took 50 working days. The process was described by the contractor as a traditional jacking job through silty clay till. Since the cylinders of the jacking machine required more space than was available in the working shaft, the contractor built a 3-metre “tail tunnel” that extended beyond the circumference of the working shaft. The tail tunnel accommodated the cylinders of the jacking equipment. Once the pipe jacking was completed, the metal lined tunnel was completely filled and covered by steel wall plates. The jacking pipe was 1200 mm diameter pipe supplied by Hanson.

Niran Construction Limited of Toronto, under the supervision of David Schaeffer Engineering Limited (consulting engineer for Mattamy Development Corporation), constructed the drop structure, inlet, and outfall to the Rouge River in approximately four months.

The precast concrete drop structure is believed to be the deepest in Canada for completing a stormwater management system for a residential development. Precast concrete manhole components and standard concrete drainage and jacking pipe proved to be an easily installed, economical, long-term solution.


Albert Wissa, P.Eng., is with Niran Construction
Kent Campbell is with Hanson Pipe & Products Canada Inc.
Contact: kent.campbell@hansonamerica.com


See our home page on how to order your subscription. We regret we can only accept orders from Canada.