Environmental Science & Engineering - www.esemag.com - July 2005
Comments? send them to the editor.

Storm sewer rehabilitation using shotcrete lining

By Jonathan Knoyle, R.V.Anderson Associates


The City of Ottawa recently completed the rehabilitation on Belcourt Boulevard of a corrugated steel storm sewer, a section of which was restored using a shotcrete lining technique. The sewer was installed some 30 years ago, but had been experiencing deformation for many years. This article describes the rehabilitation evaluation and design stages, the key features of the shotcrete process and some of the issues that were encountered during construction.

The Belcourt Boulevard storm sewer services a 250 hectare catchment area in the Orleans community of Ottawa. The sewer was installed in the late 1970s as an 1,800 mm diameter corrugated steel pipe (CSP), with a 1,981 mm diameter outfall under St Joseph Boulevard. During pipe installation, deformation occurred and wooden struts were installed to restore the pipe shape. Additional aluminium struts were installed in 1999 to arrest continuing deformation.

Under two separate contracts in 2002 and 2003, R.V. Anderson Associates Limited (RVA) were engaged by the City of Ottawa to design the opencut replacement of 560 m of CSP on Belcourt Boulevard with concrete pipe. In January 2004, RVA were retained to develop a solution for the rehabilitation of the remaining downstream section of culvert under St Joseph Boulevard, and this is the subject of this article.

The 73 m long outfall sewer was bitumen lined with two 45-degree horizontal elbows between the outfall headwall and the upstream maintenance hole, which was located in a busy 6-lane traffic intersection (including a turning lane and a bus lane), with extensive underground utilities. The outfall contained 60 aluminium adjustable struts bearing onto continuous timber header and footer plates. Local storm and sanitary sewers, a Bell fibre optic duct, a gas supply main, 406 mm and 610 mm (high pressure) water mains and Hydro lines were situated above the sewer in the road corridor.

The City of Ottawa prioritized this section of outfall sewer for restoration because:
Rehabilitation options
It was realized that due to the proximity of extensive street utilities and the potential traffic impacts, an open-cut sewer replacement might not be the most effective rehabilitation method. Therefore, 11 alternative rehabilitation methods were considered, including shotcrete lining, tunnelling, slip lining (with rigid and flexible pipe), liner plate lining, cured-in-place lining, high-level overflow sewer and full sewer relocation, and combinations thereof.

A two-staged evaluation process was used involving an initial screening stage, in which the advantages and disadvantages of each option were investigated, followed by a detailed assessment of the four best options. The short-listed options were: shotcrete lining, liner plate lining and open-cut sewer replacement (along the existing and new alignments). The detailed evaluation criteria that were applied included: For each of the criteria, the relative merit/impact of each option was assessed and a rating of 3 (favourable), 2 (no significant advantage/disadvantage) and 1 (unfavourable) were applied. Double scores were adopted for the first three criteria, since these were of greatest importance to the rehabilitation solution. The final rating scores and construction cost estimates of the shortlisted options were as shown in the table.


It was recognized that the life expectancy of the shotcrete solution might be inferior to that of new sewer pipe and that this would affect the overall life-cycle costs. However, other initiatives, such as the City’s asphalt overlay, Hydro’s facility upgrades on St Joseph Boulevard and the need to relocate a watermain prior to open-cut trenching, dictated that an immediate solution was preferable and so shotcrete lining was recommended as the best method of rehabilitation.

Design of shotcrete lining
Shotcrete sewer lining was used by the City of Ottawa in 2000 to rehabilitate a similar CSP culvert. Details of this previous project were investigated to see what lessons could be learned and a site visit was arranged so that the lining could be inspected. Based on RVA’s findings, the following items were identified as being key to the success of the current project: If the struts were removed and a concrete lining formed, the design flow of 12.0 m3/sec could be conveyed through a 1,550 mm diameter conduit. In the most deformed area, the CSP was 1,764 mm high and so pipe hydraulics governed that 100 mm thickness of shotcrete would be applied to the top and bottom of the pipe, with 225 mm of reinforced shotcrete at the spring lines for structural strength. This application was continuous throughout the complete length of the sewer outfall. To avoid culvert collapse during construction and to provide continuity of re-bar, the design allowed for every sixth strut to be removed prior to shotcreting. Once the lining had cured, all remaining struts, plus the continuous header and footer plates, would then be removed and the spaces grouted.

Access into the culvert was provided from a platform in Bilberry Creek.

Approval for construction work in the vicinity of the creek was obtained through the local Conservation Authority. The City of Ottawa also obtained temporary easements for construction access through private land to the headwall in Bilberry Creek.

Contract specifications and drawings for the shotcrete rehabilitation work were prepared by RVA and the project was tendered. Due to the specialist nature of this work, only two tenders were received and the contract was awarded to Underground Services (1983) Ltd. (USL) from Toronto for a price of $281,400. Construction work commenced early in October 2004.

Construction
Access into the culvert during construction was provided by a temporary structure erected in the bed of the creek.

The contract called for the installation of a temporary flow bypass into Bilberry Creek at an approved upstream location. However, USL proposed an alternative bypass system comprised of a weir in the upstream maintenance hole with a series of pipes laid through the culvert to convey the flow. This was considered to be an environmentally preferred alternative and was accepted. However, only a small proportion of the culvert’s flow capacity could be conveyed through the temporary bypass lines. Therefore, monitoring of weather conditions during construction and timing of the key phases of work were critical to ensure that during peak rainfall events, the weir could be quickly removed and the flow conveyed safely through the culvert without damaging the infrastructure.

A ‘wet shotcrete’ method was used and stainless steel threaded rods were tack welded onto the CSP with adjustable nuts, to control layer thicknesses. The shotcrete was applied in longitudinal sections, with the culvert invert being shot first, between the 4 o’clock and 8 o’clock positions in two, 50 mm lifts. Layering continued up the side of the culvert to achieve the required thickness at the spring lines. Using the previous lifts for support, thin layers were then applied over the top half of the culvert until the complete circumference was lined. Guide wires were installed between threaded rods to control the surface of the finish coat. The final lift, below the spring line, was brush finished.

During construction, USL modified the strut removal process to provide a more robust permanent reinforced lining. Instead of shotcreting up to the timber header and footer plates, USL were able to cut out the plates between struts prior to shotcreting and provide temporary longitudinal strut support so that full-circumference steel reinforcement could be installed throughout the complete length of the culvert.

The project was substantially completed within six weeks at no extra cost to the contract price.

Conclusion
This project used an innovative rehabilitation approach to overcome some difficult site constraints and provide the City of Ottawa with a storm sewer capable of meeting the required level of service. A key component in the success of this project was the ability to learn from the previous culvert shotcrete project to develop an effective design. The City realized the following benefits: Condition monitoring of the concrete lining over the coming years will be carried out to verify the durability of the shotcrete lining.


Jonathan Knoyle, P.Eng., is an Associate of R.V. Anderson Associates Limited in Ottawa and was Project Engineer on the St Joseph Boulevard Storm Sewer Rehabilitation project.
E-mail: jknoyle@rvanderson.com.
The Project Manager at the City of Ottawa was Jamie MacDonald, P.Eng.


See our home page on how to order your subscription. We regret we can only accept orders from Canada.