Environmental Science & Engineering - www.esemag.com - November 2003
Comments? send them to the editor.

CSO project in Portland benefits from environmental engineering

Paul G. Cummins,
Baker Tanks

A diver prepares to go into the Nicolai Shaft in early May 2003.
Photo: Sue Bednarz
It is hard to imagine the type of municipal infrastructure required to manage the Pacific Northwest’s annual heavy rainfall. One of the situations plaguing a seasonally waterdrenched city is a combined sewer overflow (CSO) which occurs because combined sewer pipes are not large enough to carry both stormwater and sanitary flow to the treatment plant. During a CSO, stormwater fills the combined sewers. The overflows carry bacteria from the untreated sewage, as well as other stormwater pollutants directly into the river.

In 1991, the city of Portland, Oregon’s Environmental Services division recognized the need to reduce its CSOs from the nearby Columbia and Willamette Rivers. To date, Portland has reached the halfway mark in its 20-year effort to stem CSOs - completely stopping the CSOs from the Columbia Slough and now concentrating on the Willamette River projects.

Geology proves challenging
One of the main projects is the building of the West Side pipeline, a $293 (US) million sewer improvement dubbed by locals as the “West Side Big Pipe.” One of the main contributors to the West Side CSO’s construction success is Baker Tanks, who provide temporary liquid and solid containment rentals.

The West Side CSO is a project designed to reduce the volume of untreated combined sewage that overflows into the Willamette River during rainstorms. Attesting to the environmental effectiveness of this operation, the prior Columbia Slough project reduced CSOs to the Slough by 99 percent. Additionally, over the past 11 years, Portland’s Environmental Services has removed 1.8 billion gallons of stormwater from the combined sewer system and has reduced total CSO volume by 53 percent annually.

The undertaking - the largest public works project in the city’s history - includes building an 18,500-foot pipeline on the west side of the Willamette River, and a large pump station on the east side of the river on Swan Island in North Portland.

The Nicolai Street shaft is the first of four access shafts to be built that connect to a 120-foot deep, four-mile long, 14-foot diameter tunnel at various locations along the alignment. The shafts will be used for a variety of functions such as providing personnel and equipment access, surge storage capacity and air venting. The Swan Island pump station will eventually be the connecting point between the east and west side sections of the CSO project. The east side section is still in the design phase.

The general contractor for the project is a joint venture between two companies, Impregilo and S.A. Healy. Impregilo is an Italian firm with extensive mining experience, while S.A. Healy, Impregilo’s Chicago-based sister company, has extensive underground construction experience. There are only a handful of firms in the world that can do this kind of specialized work.

“The geology on this job is extremely challenging,” notes Jim McDonald, project manager for Impreglio/S.A. Healy. “All of this work is being performed in silt and sand that is below the water table. The soil is extremely wet and very permeable which makes it difficult to excavate. To support the excavation, we are using a variety of deep foundation techniques that are cutting edge, such as slurry wall construction and jet grouting.”

McDonald adds that they have generally been able to control the water from the deeper shaft and tunnel construction without having to discharge it. However, surface excavations have resulted in large amounts of water that must be filtered and disposed of in an environmentally compliant manner.

“We use Baker Weir tanks for filtering the sediment from the groundwater,” he says. “A big advantage is that we’re working in an urban area and these steel tanks take up a smaller footprint than others. We’re able to run our discharge water through the Baker Weir tanks, then release into the city sewer. The six sites on this job each have a number of their tanks because even if we don’t get water when we excavate, we have to be prepared in case we do.”

Providing an efficient solution
To stabilize the porous ground and construct the shafts, Impreglio/S.A. Healy called upon a joint venture of subcontractors Bencor, Petrifond, and Pacchiosi to perform the $50 (US) million slurry wall construction and jet grout ground improvement. “We have been using as many as seven Baker EZ Access tanks in each location,” says Vince Luongo, Bencor, Petrifond, and Pacchiosi project manager. “The Baker tanks contain the bentonite that stabilizes the trenches that we’re excavating to form the Nicolai shaft construction for the tunnel-boring machine (TBM) entry.” In August 2003, the contractors used the Nicolai shaft as a launching point for two TBMs - one tunneling north and the other tunneling south - to build the CSO tunnel. The tunnel-boring machines were specially manufactured in Germany for this project.

To assemble the sophisticated equipment below ground, the Impreglio/Healy crew lowered the machine parts - the largest weighing in at 85 tons - a piece at a time to the bottom of the 60-foot-wide shaft. The 10-man team of mechanics and labourers then hooked up motors, attached hydraulic hoses, programmed the guidance system, and connected the water and slurry pipes.

Custom manifolds connect pumps and filtrations systems on the east and west sections of the project.

Once assembled, the TBMs began chewing a tunnel 16 feet in diameter through the earth. “The machines bore at one end and spit out the 3- to 5-foot-long concrete pre-cast pipe rings at the other,” says McDonald. “After we install the 14-foot diameter concrete lining at the tail of the machine, hydraulic jacks move the cutter forward and make room to install the next ring.”

Using this method, it is estimated that it will take about 11 months to bore the north tunnel to Swan Island; the south tunnel is expected to take 23 months.

Baker's local branch in Portland, Oregon provided the 21,000-gallon EZ Access tanks to assist with the solids and liquids containment on the construction site. The tanks’ four proprietary hinged deck lid panels lift up for a visual inspection of all the internal contents. Additionally, Baker installed 6-inch valves to customize each tank for the job.

Creating innovative solutions
Of special note is Bencor, Petrifond, and Pacchiosi’s jet grouting process. The jet grout process involves pumping high-pressured air, water and cement into the 330 feet deep holes. This has only been done a few times at this depth. The air and water erode the soil in a column form. Then the soil is flushed out of the ground to the surface and the jets backfill behind the flushed soil with the grout to form a stabilized, cemented ground. The result is a water-impermeable ground well suited for excavation and construction.

Contact: pcummins@bakertanks.com.

See our home page on how to order your subscription. We regret we can only accept orders from Canada and the United States.