Environmental Science & Engineering - www.esemag.com - November 2005
Comments? send them to the editor.


Design-Build – does this method work well in the public sector?

By Eric A.D.MacDonald, M.Sc., P.Eng.
Chairman and CEO MacViro Consultants Inc.

For the past decade and on a selective basis, the public sector has employed the design/build (D/B) method of project delivery in lieu of the conventional method. The main difference between the two delivery modes is that the contractor is ‘given’ the works at the beginning of the design phase rather than with the conventional approach, whereby the contractor comes on board at the end of the design phase. This difference is highly significant to the success of the project, because the public sector and the D/B contractor have different objectives, i.e. the public sector client wants a project that has low life-cycle costs while the D/B contractor wants a project that has low capital costs.

Why then would the public sector client select the D/B approach for their project? The answer is that the public sector believes that the D/B project delivery model gives an accelerated schedule, known up-front costs, no extras and reduced overall costs.

The misconceptions and realities of these beliefs, which have been realized, are: The conclusions that are now emerging are that the D/B method of project delivery is on a down-cycle for the following reasons:
  1. It is perhaps fair to conclude that although the D/B project delivery mode may apply to projects for the private sector, it does not work well for the public sector.
  2. The public needs are best addressed through the conventional approach, where the design consultant is much more sensitive to the ‘soft’ but critical considerations of a project.
  3. If a D/B project delivery mode is to be selected, it must include up-front comprehensive data so that the D/B contractor can fairly price the works and thereby obviate future claims.
  4. A ‘partnering’ concept is critical, considering the initial data transfer is rarely complete. Accordingly, the working relationship with the contractor must be one of close co-operation rather than one of antagonism.
  5. The Expression of Interest must fully define the subsequent Request for Proposal requirements, including a comprehensive risk-sharing matrix.
In summary, and with the D/B project delivery mode in decline, what is now increasingly appearing on the project delivery scene is perhaps the 3Ps, i.e. public-private partnerships, a model that depends on co-operation and equitable risk sharing. Accordingly, it appears that there continues to be a need for the private sector to be involved with public sector works.

Some ten to fifteen years since the ‘arrival’ of privatization, it is quite reasonable to assume that the PPP project delivery model may be the next preferred approach.


Contact: esaar@macviro.com

See our home page on how to order your subscription. We regret we can only accept orders from Canada.